TAURON battery energy storage programme with NFOŚiGW co-financing (11 facilities, 346.8 MW / approx. 1.5 GWh)

in progress
funding: EU funds

A package of 11 TAURON Group battery energy storage facilities with a combined power of 346.8 MW and a capacity of approx. 1.5 GWh, covered by a single co-financing call of the Modernisation Fund, operated by NFOŚiGW. The projects were qualified for support in December 2025, and on 30 December 2025 TAURON Zielona Energia and the special-purpose companies TAURON BME 4, BME 8 and BME 9 signed agreements for a total of PLN 537.75 million, covering 35 to 45 percent of the cost of the individual investments. The largest sites are Laryszów (84 MW / 358 MWh), Ogrodzieniec (55 MW / 237 MWh) and Bałków (54 MW / 242 MWh); the others are Twardogóra, Dąbrowa Środkowa, Stare Bogaczowice, Bytom, Kuźnia Raciborska, Baranowice, Pilchowice and Radlna Tarnowiec. Construction is planned for 2026–2028. According to the report for the first half of 2026, the Kuźnia Raciborska facility (6.9 MW) was 96 percent complete and due for completion in the third quarter of 2026. The other projects were at an early stage, with most of them due for commissioning in 2027–2028. The total cost of the programme has not been published.

How it went

We have assessed this project, but none of the four axes is shown here: 3 carry no assessment yet, one has an assessment with no confirmed quote. The timeline and sources below show what is known about it. How to read this section

Timeline

  1. AnnouncedDec 2025
  2. Original date2028
  3. Current date2028

Significance

The programme is to add 346.8 MW of battery storage capacity in the Śląskie, Dolnośląskie, Świętokrzyskie and Małopolskie voivodeships. According to TAURON, the facilities are to provide system services, increase the grid's capacity to take in renewable energy and lower balancing costs. The package counts towards the TAURON Group strategy target for 2025–2035: 700 MW of battery storage capacity by 2030 and 1.4 GW by 2035.

Sources 8 · 7 independent · 4 archived

Every fact on this card comes from the sources below. Next to each source – which fields it supports.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. TAURON Polska Energia (biuro prasowe)30 Dec 2025
  2. Rzeczpospolita (energia.rp.pl)16 Dec 2025
    Original date
    Original dateŚrodki przyznane w ramach dofinansowania zostaną przeznaczone na budowę 11 bateryjnych magazynów energii o łącznej mocy 346,8 MW, których budowa przewidziana jest na lata 2026–2028.
  3. WNP.pl30 Dec 2025
    InvestorFunding
    InvestorTauron Zielona Energia oraz spółki celowe (Tauron BME 4, Tauron BME 8 oraz Tauron BME 9) podpisały umowy na dofinansowanie na poziomie od 35 proc. do 45 proc. dla 11 swoich inwestycji o łącznej mocy ponad 346 MW i pojemności ok. 1,5 GWh.
    FundingŁączna kwota, którą otrzyma grupa, wyniesie 537 754 312,37 zł.
  4. Inżynieria.com9 Dec 2025
    Announced
    AnnouncedSpółka Tauron uzyskała pozytywną ocenę dla 11 projektów bateryjnych magazynów energii i został zakwalifikowany do otrzymania blisko 538 mln zł dofinansowania z Funduszu Modernizacyjnego
  5. Gramwzielone.pl24 Sep 2026
    StatusCurrent date
    StatusPozostałe projekty są na wczesnym etapie prezentujemy poniżej. Zakończenie realizacji i przekazanie do eksploatacji większości projektów zaplanowano na lata 2027–2028.
    StatusPoza Dąbiem i Przewozem (po 4 MW, oba ukończone i przekazane do eksploatacji w lutym 2026 r.) najbliżej zakończenia są dwa projekty: BME Kuźnia Raciborska (6,9 MW, nakłady 15,3 mln zł, zaawansowanie 96 proc.) oraz BME Proszówek (9,5 MW, nakłady 12,4 mln zł, zaawansowanie 96 proc.). Oba mają zostać ukończone w III kwartale 2026 r.
    Current dateZakończenie realizacji i przekazanie do eksploatacji większości projektów zaplanowano na lata 2027–2028.
  6. TAURON Polska Energia (biuro prasowe)8 Dec 2025
  7. enerad.pl9 Dec 2025
  8. Green-news.pl12 Dec 2025
    AnnouncedFunding
    Announced · FundingTylko Tauron dla swoich 11 projektów magazynów energii zabezpieczył ponad 537 mln zł finansowania.